Grey County is getting a new maintenance depot in Durham.
The new facility will be built for just under 1.4 million dollars — slightly under budget.
Chatsworth Mayor Howard Greig says the county had to do some negotiating when the original bid from Domm Construction of Ayton came in over budget.
A revised bid was tendered after the elimination of a sand storage building, one of the truck bays and a generator.
Greig says the new depot will replace the current facility in Durham, which is being moved to Ayton.
The cost of the project is being split three ways between the municipality, the province and the federal government.